Our building's defects-liability period is about to end — after that, who's responsible for fixing things?
We took handover of our villa just under a year ago, and I've realised the defects-liability period is about to end. Up to now the developer has fixed snags, but I'm not clear what happens after it expires.
Who's actually responsible for fixing things then — us, the developer, or the owners' association? And is there anything I should do before the deadline to protect myself?
2 answers
Good that you've spotted the deadline — a lot of people miss it and lose their leverage. Here's how it works:
During the defects-liability period (DLP) — usually 12 months from handover (check your SPA/handover docs for the exact term) — the developer or contractor is obliged to fix genuine defects (workmanship, materials, MEP faults) at no cost to you. That's the window you're in now.
Once the DLP ends: - That free-fix obligation stops. Anything that fails afterwards inside your unit is generally your responsibility. - For common areas (facades, lifts, shared MEP, roof, pool), responsibility sits with the owners' association / building management, funded by service charges — not the developer. - Structural issues can carry a separate, much longer liability (often ten years — the "decennial" cover) in some contracts, but everyday finishing and MEP defects do not.
What to do BEFORE the deadline (the important bit): 1. Re-snag the whole unit now, room by room, exactly like the original handover — a year of living in it surfaces things the first snag missed (settlement cracks, doors dropping, silicone failing, small AC/plumbing niggles). 2. Submit everything as one written, photographed list before the expiry date, so it's on record as raised *within* the period. 3. Push to have it all fixed (or at least formally acknowledged) before the clock runs out.
Then, for afterwards, line up your own cover — an annual maintenance contract, or a finishing and snagging team you can call for the finishing and snagging work that's now on you. Getting a proper re-snag done in these last weeks is the single highest-value thing you can do.
The re-snag before expiry is exactly right and worth repeating: the developer only owes you what you've logged in writing within the period, so a verbal "they said they'd sort it" counts for nothing once the date passes. I'd add — get written confirmation of the exact DLP end date from the developer or management now, photograph every defect with a date, and don't accept "we'll come after we hand over the next phase." If it isn't fixed or formally logged before the deadline, it becomes your bill.
People also asked
- New building still under warranty — do I still need a maintenance contract (AMC)?3 answersApartment & Office Renovation
- How do you switch maintenance providers without a gap in cover or losing service history?3 answersApartment & Office Renovation
- The developer is dragging on fixing my snags after handover — how does the defects-liability period actually work?3 answersApartment & Office Renovation
- Taking handover of a new-build villa — what must be on the snag list before I sign and pay?5 answersApartment & Office Renovation
- Business Bay office, months after the fit-out little things are showing up (doors, AC balance, snags), whose job is the aftercare?2 answersApartment & Office Renovation
- One handyman for everything, or separate specialist trades — when is a handyman actually the right call?2 answersApartment & Office Renovation
More in Apartment & Office Renovation
- Want to freshen up our apartment kitchen and bathroom without a major renovation — what's realistic (and NOC-free)?2 answersApartment & Office Renovation
- Just bought our first Dubai home — how should we actually budget for annual upkeep, and what are the big costs?2 answersApartment & Office Renovation
- Handover snag list — what finish and paint defects do inspectors actually flag that I'd miss myself?3 answersApartment & Office Renovation
- Rain forecast after weeks of dust — what should I actually check around the villa before the first rain hits?3 answersApartment & Office Renovation
- Just got the keys to a Dubai villa — what do I sort with DEWA and check in the first week?3 answersApartment & Office Renovation
- Buying a resale villa in Dubai — what maintenance and condition checks should we do before we commit?3 answersApartment & Office Renovation