How do you avoid getting overcharged or stuck mid-renovation?

Omar K.HomeownerBudget-mindedPosted 28 May 20262k viewsActive

Everyone has a horror story about a renovation that ballooned in price or a contractor who vanished mid-job. For those who've done it — how do you structure the quote and payments to protect yourself?

3 replies

Fatima Z.
Expert28 May 2026

The contract structure is your protection, not the person's charm:

  • Itemised fixed-price quote, not a lump sum. Every line (demo, MEP, tiling, joinery, paint) priced separately, so you can see what changed if it changes.
  • Stage payments tied to milestones — deposit, on first-fix complete, on tiling complete, on handover. Never pay most of it upfront; a contractor funded at the start has no reason to finish.
  • Trade licence + written scope, including what's *excluded*. Most 'overcharges' are really 'that wasn't in the scope' surprises.
  • Retention — hold back a small final payment (5–10%) until snagging is done.

Get three itemised quotes and compare line by line — the cheapest lump sum is usually the one that balloons.

Jason S.
Homeowner29 May 2026

Retention saved me — held the last 10% until snagging, and suddenly the little unfinished bits got finished fast. Also: get variations (extra work) priced in writing *before* they do them, not after.

Priya N.
Homeowner30 May 2026

Paying in stages against completed work is the big one. A friend paid 80% upfront 'for materials' and the guy disappeared. Never again.